tall buildings

Is the Building Safety Act really stopping tall buildings?

Newsletter sign-up

Sign up to our newsletter to receive updates on our latest news for lenders, landlords, occupiers and developers.

Name
This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.

Since the Building Safety Act 2022 introduced a new approval regime for higher-risk buildings, many developers have concluded that tall residential schemes are too slow, too uncertain and too complex to be worth pursuing. That uncertainty has made some funders more cautious, particularly where they lack in-house expertise in the regime.

That view is understandable, but the picture in autumn 2026 is more nuanced. Approval times at the Building Safety Regulator have roughly halved over the past year and approval rates have risen sharply. Meanwhile, new fire safety guidance on staircases and the Building Safety Levy have changed the design and cost baseline for many schemes. The final stage of the regime, Gateway 3, has also yet to be tested on a completed new build.

Tall buildings can still be delivered. What has changed is the discipline required to deliver them. The schemes best placed to succeed are those where design, evidence, programme, contracts and funding have been aligned with the regime from the outset.

Gateway 2 is faster, but still a programme risk

The regime applies to higher-risk buildings, which broadly means buildings at least 18 metres high or with at least seven storeys that contain at least two residential units. Before work starts on a new building of this kind, the client must obtain building control approval from the Building Safety Regulator. This is Gateway 2. The regulator’s guidance allows up to 12 weeks to assess a new build application unless an extension is agreed. In practice, that has proved to be a target rather than a reliable turnaround time.

The latest figures are encouraging. In the 12 weeks to 31st  August 2026, the regulator made 50 decisions on new higher-risk buildings and conversions, approving 46 of them. That is an approval rate of 92 per cent once invalidated and withdrawn applications are excluded. The median approval time was 22 weeks. A year earlier, the equivalent figures were 43 weeks and 39 per cent.

The improvement has come in the year since the regulator set up its Innovation Unit in August 2025 to deal exclusively with new build applications. It has also changed status. Having previously sat within the Health and Safety Executive, it became a standalone arm’s-length body under the Ministry of Housing, Communities and Local Government on 27th January 2026.

The workload is still considerable, however. At the end of August, 147 new build and conversion applications were in progress, and 1,654 Gateway 2 applications were live across all categories. For appraisal purposes, a Gateway 2 period of several months remains the realistic assumption. Land and development agreements, facility conditions, drawdown mechanics and longstop dates are all worth testing against that timetable now, together with the carrying costs it implies. Discovering the gap once the application has been submitted is far more expensive.

Application quality is the risk developers can control

Delay is not only a question of the regulator’s capacity. When an application arrives, the regulator first checks that the required information has been provided, and it may ask for more or reject the application if something is missing. Its guidance also makes clear that assessment time depends partly on the quality of the application and the complexity of the work. The House of Lords Industry and Regulators Committee reached a similar conclusion in December 2025, finding that basic errors and an inability to evidence fire and structural safety were contributing to delays and rejections.

A Gateway 2 application is much more than a set of drawings. It must explain how the building will comply with the Building Regulations. That explanation is supported by a series of plans and statements covering how construction will be controlled and how changes will be managed. They also address the competence of the key duty holders and the fire safety information for the completed building. Those documents need to tell a consistent story and lead the regulator to the evidence behind the compliance case.

For developers, this is one of the few parts of the process genuinely within their control. A readiness review before submission is time well spent, provided it tests whether the evidence is complete and consistent rather than simply whether every document has been uploaded. Safety-critical design interfaces, responsibility for any outstanding information and the approach to later changes are all better resolved before the application goes in. For funders, the more revealing question is how that review was carried out and what remains open, rather than the target submission date alone.

Staging and approval with requirements

Two mechanisms in the current guidance can help work get under way before every later element of a project is finalised. They are often spoken of together, but they work differently.

A staged application divides the work into separate stages, each with its own detailed plans. Stages are assessed and approved in turn, and work on a stage cannot start until that stage has been approved. The regulator considers staging proposals case by case, and may take up to 12 weeks to assess each stage unless an extension is agreed.

Approval with Requirements is different. It is a type of decision on an application, rather than a way of structuring one. Work can begin on the parts that have been approved, but not on any part subject to a requirement until the regulator is satisfied that the requirement has been met. It is not a planned route for leaving core design questions unresolved.

Used well, staging can improve cash flow and reduce time lost waiting for approval, particularly where the stages are technically coherent and the first stage is genuinely complete. It also adds assessment points and dependencies of its own. A staging strategy therefore works best when it is developed alongside the design and construction programme, discussed with the regulator early, and reflected in the contract and funding milestones.

Beyond Gateway 2

Faster approvals do not resolve every issue in a tall building appraisal. Two further changes, one to design guidance and one to cost, now affect schemes regardless of how quickly Gateway 2 is achieved.

From 30th September 2026, updated Approved Document B guidance recommends more than one common stair in a block of flats with a top storey at least 18 metres above ground level. Approved Document B is statutory guidance on meeting the Building Regulations rather than legislation in its own right, but for most schemes it will be the starting point for demonstrating compliance.

Schemes already in the pipeline may still be able to follow the previous guidance. That depends on the relevant building notice, initial notice or full plans application having been made before 30th September 2026, and on the work being sufficiently progressed before 30th March 2028. For a new building, sufficient progress is tied to the start of pouring concrete for the permanent foundations, or to the permanent placement of piling.

Relying on the transition therefore raises two separate questions. One is whether the scheme meets the legal conditions. The other is whether the programme can realistically reach the construction milestone in time, given how long Gateway 2 actually takes. If the answer to either is no, a redesign may affect the core, the net saleable or lettable area, the unit mix, the services strategy, the planning position and ultimately viability.

Where the transition is available, it is still worth testing a single-stair design with the scheme’s funders, insurers, investors and intended exit market. How each of them views such a building is a due diligence question for the particular scheme, and one that is better answered early than at the point of sale or refinancing.

The levy changes the appraisal

The Building Safety Levy came into operation on 1st October 2026. Broadly, a charge arises where the works form part of a major residential development, create new residential floorspace and are carried out for a client who is not exempt. Detailed exclusions and exemptions also apply. A major residential development is one with planning permission for at least 10 new dwellings or at least 30 bedspaces of purpose-built student accommodation. Dividing a scheme into smaller building control submissions does not avoid the threshold where the planning permission is for a major development.

The levy is charged per square metre, at rates that vary by local authority area, use and site status. Certain uses and some forms of affordable and supported housing are excluded or exempt, and qualifying previously developed land benefits from a discounted rate. Responsibility for payment falls on the client identified for building control purposes, while the local authority collects and administers the charge.

Timing matters as much as amount. The whole levy charge for an application must be paid before a completion certificate can be issued for any of the works within that application. That makes the levy a completion and cash flow issue as well as an appraisal cost, particularly for schemes with a partial completion strategy.

Applications made before 1st October 2026 remain outside the levy, even if they are varied after that date. An application that was rejected and resubmitted on or after 1st October, however, is liable. Developers who submitted ahead of the deadline will want to be confident that their applications met the required standard.

Gateway 3 is the next major test

At completion, a higher-risk building needs a completion certificate before it can be registered for occupation. As of 31st August 2026, the regulator reported that no new build project that had passed through Gateway 2 had yet reached Gateway 3. That does not mean Gateway 3 will be slow. It does mean there is not yet a body of completed new build cases from which developers and lenders can judge the likely timetable, or the evidence the regulator will expect in practice.

Much of the risk at completion is created during construction. The construction control plan must explain how evidence of compliance and as-built information will be gathered as the work progresses. Changes must be recorded, and major changes need approval before the affected work goes ahead. Notably, the regulator’s inspections have already identified a small amount of new build work that departed from the design agreed at Gateway 2.

Those realities need a home in the transaction documents. Contracts and development facilities work best when they are clear about who is responsible for each part of the evidence record. They also need to settle who bears the cost and programme consequences of an unapproved change. The final question is what happens if a delay in certification or registration pushes back occupation, practical completion under an agreement for lease, repayment or exit.

The rules are still developing

The framework has not yet settled. In July 2026, the government published its response to a consultation on making the treatment of work to existing higher-risk buildings more proportionate. It is minded to take most work within individual flats out of the full Gateway 2 process, although that will require a statutory instrument. Those proposals concern existing buildings and do not relax the current approval requirements for a new residential tower.

The government also intends to commission the independent review of the building safety regime required by section 162 of the Building Safety Act 2022 by April 2027. For schemes with a long programme, it makes sense to keep current guidance under review and to allow for regulatory change in procurement and finance documents, without assuming what the review will conclude.

Where this leaves developers and funders

So is the Building Safety Act stopping tall buildings? On the evidence, no. What it has done is make immature design, incomplete evidence and unrealistic sequencing considerably more expensive than they used to be.

A deliverable scheme now starts with a Gateway 2 programme based on current performance rather than the statutory minimum. It also needs a clear strategy for evidence and change control, a considered approach to any staging, and early answers on the staircase transition and the levy. The same discipline then needs to carry through construction, so that Gateway 3 is prepared for from day one.

For developers and funders, that changes the character of building safety. Rather than a late regulatory hurdle, it becomes a set of identifiable programme, cost and contractual risks that can be investigated, priced and allocated before capital is committed. Early legal input is at its most valuable here, turning those risks into drafting and due diligence that holds up when the programme is tested. With that groundwork in place, taller buildings remain a credible route to new homes at a time when the country needs them.